Lights Go On in the New Research Data Centre

With enormous thanks to our Estates project manager, we can confirm that the lights have gone on in the new Research Data Centre. This means ‘all systems are go’ for the BEAR migration 17th to 26th May as previously announced. See the service impacts summary published on 8th March   ‘Important! Extended Service Impacts for BEAR … Continue reading “Lights Go On in the New Research Data Centre”

Published: Posted on

Building for the future …

As the number and size of the services provided by Research Computing has grown over the past 5 years, we’ve steadily put pressure on the University’s data centres. The power consumption of CPUs have risen as servers are packed with more and more cores and, at the same time, driven by the demands of research, … Continue reading “Building for the future …”

Published: Posted on